Building permits for a house in Ontario

What needs one, what the municipality needs to see, and how long it takes.

Updated

Short answer

A new house, an addition and most structural, plumbing and heating work need a building permit. Once an application for a house is complete, the Building Code gives the municipality 10 business days to issue the permit or refuse it in writing, and the work is inspected at stages the Code sets.

What needs a permit

WorkBuilding permit
A new houseYes
An addition of any sizeYes
Removing or altering a load-bearing wall, beam or columnYes
New or enlarged window and door openingsYes
New or relocated plumbingYes
New heating and ventilation systemsYes
Underpinning or lowering a basementYes
Taking down a buildingA demolition permit
Painting, flooring and trimGenerally not
Cabinets and countertopsGenerally not
Replacing fixtures in the same locationGenerally not

The municipal building department has the final say on what needs a permit.

What a complete application includes

Application form
Signed by the owner or by an agent the owner authorizes.
Drawings
Site plan, floor plans, elevations, sections and details, to scale.
Qualified designer
An architect, a professional engineer, or a designer qualified and registered with the Province. An owner may prepare drawings for their own house.
Engineering
Structural design where the house goes beyond what Part 9 of the Building Code covers, and the heating and ventilation design.
Energy efficiency
How the house meets the energy requirements of the Building Code.
Applicable law
Every approval the permit depends on: zoning, a variance, a conservation authority permit or heritage approval.
Fees
Permit fees, and development charges where they apply.

The review period

When the clock starts
The day after the application is complete.
Time allowed for a house
10 business days to issue the permit or refuse it, with the reasons in writing.
Other buildings
15 business days for a small building, 20 for a large building and 30 for a complex building.
After comments
Once the examiner issues comments, the time frame no longer applies.

Inspections during construction

The Building Code lists the stages at which the builder must notify the municipality so the work can be inspected. On a house, the main ones are these.

Footings
Before concrete is placed.
Foundation
Before the excavation is backfilled.
Framing
When the structural frame is complete.
Plumbing and heating rough-ins
Before they are covered.
Insulation and vapour barrier
Before drywall.
Occupancy
Before anyone moves in.

Questions

Who applies for the building permit?

The owner, or an agent the owner authorizes, such as the builder or the designer. On our projects we prepare and file the application and book the inspections.

How long is a building permit good for?

A permit does not simply expire, but under the Building Code Act the chief building official may revoke it after giving notice if construction has not seriously started within six months of issue, or has been substantially suspended for more than a year.

What happens if work is done without a permit?

The municipality can order the work stopped, and work that was covered before it was inspected can be ordered uncovered. Open permits and orders also come up when a house is sold.

Sources

  1. Building Code Act, 1992, S.O. 1992, c. 23, section 8 (permits)
  2. City of Toronto, Toronto Building: legislated time frames for permit review
  3. City of Belleville, Check review periods (Ontario Building Code, Division C, Table 1.3.1.3)
  4. Norfolk County, Permit review process
  5. Ontario Building Code, Division C, 1.3.5.1 (prescribed notices for inspection)

Checked against these sources on . This page is general information about building in Ontario. It is not legal advice, and the rules change, so confirm the current requirement for your project.